ME home
 
  SME FaceBook SME Twitter SME LinkedIn RSS Feed

Subscriber or
SME Member Log On

WEB-ONLY CONTENT

Go to SME eNEWS

MINING INDUSTRY EVENTS

SEG International Expo and Annual Meeting  - Conference
Oct 14, 2018 - Oct 19, 2018
China Mining  - Conference
Oct 18, 2018 - Oct 20, 2018
Offshore Energy Exhibition & Conference  - Conference
Oct 22, 2018 - Oct 24, 2018
Silver and Gold Summit  - Conference
Oct 28, 2018 - Oct 29, 2018

METAL PRICES


Au
Ag
Pt
Pd
Ni
Cu
Al
Pb

AGGREGATES
AND MINERALS
MARKETPLACE


http://aggregatesmineralsmarketplace.com
The Mining Engineering, SME and NSSGA
Online Buyers Directory Site
The Online Global Mining and Minerals Library Site

Arch coal remains committed to Otter Creek coal mine
April 28, 2014

Despite permitting delays and setbacks that have delayed the progress of the Otter Creek coal mine in southeastern Montana, Arch Coal said it plans to proceed with the project.

The mine has already fallen more than two years behind its original permitting schedule, The Associated Press reported. State Department of Environmental Quality officials said they need more information from Arch Coal Inc. to complete their environmental study of the mine. The study must be finished before Arch can get a permit to mine an estimated 1.4 billion tons of coal it has leased southeast of Ashland near the Northern Cheyenne Indian Reservation.

The original plans had the mine opening in 2015, but now it seems it could take years to develop the mine and an associated rail line needed to ship the fuel out of Montana.

The Associated Press reported that the company continues to work with state officials and plans to submit a revised permit application later this year, Arch spokeswoman Kim Link said. A draft environmental study is scheduled to be completed by November.

Delays for large mining projects are not uncommon but the delay is an example of the challenges the coal industry is currently facing.

While U.S. coal exports surged to record levels in the past few years, much of that growth was driven by coal shipped out of the East and Gulf coasts. For now, tight port capacity is limiting further exports from the Powder River Basin, a region straddling the Wyoming-Montana border that produces the bulk of the nation’s coal.

As a result, success for Otter Creek and another large mine proposed on the nearby Crow Indian Reservation is dependent not just on what happens in Montana, but on the fate of proposed coal export terminals on the West Coast. Among those projects is an export terminal in Longview, Wash., that includes Arch as a partner.

Some state officials in Washington and Oregon have joined environmentalists in opposition to the ports. The terminals have strong backing from many elected officials in Montana and Wyoming.

Arch is also a partner in the proposed Tongue River Railroad that would link the mine at Otter Creek with outside customers.
Approval for the railroad is pending before the U.S. Surface Transportation Board.

After members of the Northern Cheyenne Tribe raised concerns about the railroad’s potential impact on American Indian cultural sites, federal officials said recently that they would conduct additional cultural resource surveys along the route beginning next month.

A draft environmental study of the railroad is due in late summer.
 